Skip To Main Content

Greenway Rail Trail Project Design Timeline Update

Last updated: November 13, 2026

Where the project stands today

The Southampton Greenway is in the engineering design phase. On January 23, 2026, Tighe & Bond completed the project's 25% Design and submitted it to the Town and MassDOT for review. Although it is called a "25% Design," this milestone represents roughly 70% of the total design work for the Greenway.

MassDOT will hold a virtual Design Public Hearing on Tuesday, December 15, 2026 at 6:00 p.m. to present the design and receive public comment. Advance registration is required. See the MassDOT hearing notice for the registration link, the hearing flyer, and instructions for submitting written comments.

Following the hearing, Tighe & Bond will complete the remaining design work and the project will be advertised for construction bids.

The project is listed on the Massachusetts Transportation Improvement Program (TIP) for fiscal year 2029, which programs approximately $16.2 million in federal and state funding for Greenway construction. With this listing, construction could begin as early as late 2028, and design is expected to be complete well in advance.

Design milestones

Milestone Status
Right of Way acquired from Pioneer Valley Railroad Complete — December 2022
Engineering firm engaged (Tighe & Bond) Complete — early 2023
Survey and base mapping Complete — 2023
Wetlands delineation Complete — 2023
Bridge and culvert condition assessment Complete — 2023
Public information session Complete — November 2023
Initial design development and environmental review Complete — 2024–2025
25% Design submitted to Town and MassDOT Complete — January 23, 2026
MassDOT public design meeting Scheduled — December 15, 2026
75% Design Upcoming
100% Design and final construction documents Upcoming
Construction advertised for bid Anticipated second half of 2028

Project updates

November 2026: MassDOT Design Public Hearing Scheduled
MassDOT has scheduled a virtual Design Public Hearing for Tuesday, December 15, 2026 at 6:00 p.m. to present the project design and receive public comment. Registration is required. See the MassDOT hearing notice for full details and the hearing flyer.

July 28, 2026: State presents design effort for the Westfield connection
At the Select Board meeting, Assistant Secretary Kurt Gaertner of the Executive Office of Energy and Environmental Affairs presented the process the Commonwealth would follow to design and permit the missing trail link between Route 10 in Southampton and Women's Temperance Park in Westfield, joined by consultants from Stantec and Brown, Richardson + Rowe. The Select Board welcomed EEA's involvement. Watch the presentation (begins at 3:34): July 28, 2026 Select Board Meeting

January 23, 2026: 25% Design submitted
Tighe & Bond completed the project's 25% Design and submitted it to the Town and MassDOT for review.

November 2023: Public information session
Engineers from Tighe & Bond led a Greenway information session attended by approximately 130 residents, presenting the survey and assessment work completed to date and answering questions about the design process.

March 30, 2023: Design timeline established
Following the Town's acquisition of the Right of Way in December 2022, the Town engaged Tighe & Bond to begin engineering design. Survey work took place February through May 2023, with wetlands delineation in early April.